CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of column reinforcements, formworks, and casting to columns projecting from 3rd floor to the 9th-floor slab have been cast.
The contractor is expected to do Formwork to columns, cutting, bending and fixing of column reinforcement. casting of columns projecting to 11th floor
The steel fixing and casting for shear walls, and lift shaft projecting from 3rd floor to the 9th-floor slab were 100% completed.
Decking to 11th floor slab, cutting bending and fixing of steel to slab
The following levels: 4th, 5th, 6th, 7th, 8th & 9th floor, formwork has been completed as steel fixing and casting of the slab has been achieved fully.
Walling is currently ongoing on the fifth typical floor.
Casting of 11th floor slab
Mechanical and electrical first fixes to the 9th floor slab and walls have been completed.