CICADA CREST APARTMENTS

As at Jan-2024

Contractor: Johkab Enterprises Ltd.
Project Start Date: 1st March 2019
Expected Construction Period: 160 Weeks
Project Outline: Construction of 120 Units: 2 Blocks each with 60 units in Kilimani.
91%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
6th to 15th floor, walling has been fully achieved for both Wing A & B
6th to 14th floor, Plasterwork has been fully achieved for both Wing A & B
All Reinforced Concrete works of the entire project have been completed to specifications.
Fabrication of Aluminum frames and Installation works to kick off.
From the ground floor up to the roof terrace, plaster works for exterior walls have been completed.
Exterior paintwork to commence in March.
6th to 14th floor, Hacking for both electrical and mechanical provisions in the walls is currently ongoing at 100% to pave the way for plaster works to kick off.

KENZI RESIDENCE

As at Jan-2024

Contractor: Nels Enterprises Ltd.
Project Start Date: October 2021
Expected Construction Period: 140 Weeks
Project Outline: Construction of 112 Units, 5 parking levels at Westland's School Lane Road.
33%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
We have been able to complete the steel fixing, formwork, and casting of the columns from Basement B03 to the 11th floor slab.
Steel fixing, formwork, and casting of the columns to be completed 100%.
Decking of the formwork to the 12th floor and steel cutting, bending, and fixing is ongoing.
Decking of the formwork to the 12th floor and steel cutting, bending, and fixing to be done to 100%.

COVO LAVINGTON

As at Jan-2024

Contractor: Hari International
Project Start Date: 23rd Feb 2021
Expected Construction Period: 64 Weeks - Commercial / 169 Weeks- Residentual
Project Outline: Construction of a 3 floor commercial Hub/ Construction of 120 units in Lavington.
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Preparations of column reinforcements, formworks, and casting to columns projecting from 3rd floor to the 9th-floor slab have been cast.
The contractor is expected to do Formwork to columns, cutting, bending and fixing of column reinforcement. casting of columns projecting to 11th floor
The steel fixing and casting for shear walls, and lift shaft projecting from 3rd floor to the 9th-floor slab were 100% completed.
Decking to 11th floor slab, cutting bending and fixing of steel to slab
The following levels: 4th, 5th, 6th, 7th, 8th & 9th floor, formwork has been completed as steel fixing and casting of the slab has been achieved fully.
Walling is currently ongoing on the fifth typical floor.
Casting of 11th floor slab
Mechanical and electrical first fixes to the 9th floor slab and walls have been completed.

COVO ARBORETUM

As at Jan-2024

Contractor: Nels Enterprises Ltd.
Project Start Date: October 2023
Expected Construction Period: 112 Weeks
Project Outline: Construction of 15 floors in Kileleshwa
10%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
Project excavation of 30,000 Cubic meters of rock is nearing completion, currently streaming of the edges is ongoing.
Completion of the excavation.
The tender process & evaluation for the construction works were concluded and the contract was awarded to MS NEL Enterprise Ltd
Contractor to take site possession and start the pre-commencement preparations
A topographical survey was conducted to establish excavation control points to ensure the accuracy of the excavation extents. Thereafter, earthwork analysis and reports were submitted by consultants
Setting out of foundations and confirming the levels of the excavation depths