CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Gitanga Road Alucobond & Aluminum works done 99%.
• Gitanga Road Alucobond & Aluminum works to be done 100%.
• Paint works on ground 1st & 2nd floors done 85%
• Paint works to ground floor walls to be 100%.
• Othaya Road alucobond and aluminum works completed 98%
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 95%.
• Front shops aluminum and glass installation to be 100%.
• Basement floor wall and ceiling plaster works done 95%.
• Plaster works on Ground, 1st & 2nd floor shop units to be complete and paint works to be proceeding.
• Waterproofing of the 3rd floor completed and screeding done 90%.
• Basement floor wall and ceiling plaster works to be done 100%.
• External civil works done on Gitanga & Othaya side on the road reserve done 98%.
• External civil works on the road reserve to be 100% complete.
• Final manhole connection to be complete to the final manhole.
• Manhole covers installation for all external parking area manholes.