COVO COMMERCIAL

As at Feb-2023

Contractor: Skysite construction Group LTD
Project Start Date: 23rd February. 2021
Expected Construction Period: 116 weeks
Project Outline: Construction of a 3 floors commercial hub
98.7%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Gitanga Road Alucobond & Aluminum works done 99%.
• Gitanga Road Alucobond & Aluminum works to be done 100%.
• Paint works on ground 1st & 2nd floors done 85%
• Paint works to ground floor walls to be 100%.
• Othaya Road alucobond and aluminum works completed 98%
• Othaya Road alucobond and aluminum works completed 100%
• Ground floor shops aluminum framings and glass installation done 95%.
• Front shops aluminum and glass installation to be 100%.
• Basement floor wall and ceiling plaster works done 95%.
• Plaster works on Ground, 1st & 2nd floor shop units to be complete and paint works to be proceeding.
• Waterproofing of the 3rd floor completed and screeding done 90%.
• Basement floor wall and ceiling plaster works to be done 100%.
• External civil works done on Gitanga & Othaya side on the road reserve done 98%.
• External civil works on the road reserve to be 100% complete.
• Final manhole connection to be complete to the final manhole.
• Manhole covers installation for all external parking area manholes.

COVO RESIDENTIAL

As at Feb-2023

Contractor: Skysite construction Group LTD
Project Start Date: 23rd February. 2021
Expected Construction Period: 120 weeks
Project Outline: Construction of 120 units in Lavington
48%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Waterproofing of the floors to prevent water ingress.
• Screeding of the waterproofed floors.
• Arrangements for procurement of materials for subsequent floors
• Delivery of the required materials to support ongoing works to be underway.
• Casting of the amenities floor completed
• Casting of the 4th floor slabs

CICADA CREST APARTMENTS

As at Feb-2023

Contractor: Skysite construction Group LTD
Project Start Date: 1st March 2019
Expected Construction Period: 180 weeks
Project Outline: Construction of 120 units: two blocks each with 60 units in Kilimani
89%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Reinforcement and casting of the 15th floor section A to be 100% done.
• Casting of columns, the 14th floor section B to be 100% done
• 13th floor slab formworks and reinforcements done 100%
• Formworks to the 14th floor slab to be 50% done.
• Mechanical and electrical installations for 13th floor wing B completed.
• Reinforcement to the 14th floor slab wing B to be 30%
• Walling on the 8th typical floor done 85%
• Plaster works to the floor units to be on the 8th floor to be 100%.
• Plaster works to the 7th floor units Section A & B 95% done
• Plaster works to the 7th floor units Section A & B 100% done.
• Showhouse done 99% for furnishing
• Furniture installation in the showhouse to be done.

KENZI

As at Feb-2023

Contractor: Nels Enterprises Limited
Project Start Date: October 2021
Expected Construction Period: 118 weeks
Project Outline: Construction of 112 units, 5 parking levels in Westlands along School Lane
30%

Progress Video

Progress Photos

CURRENT PROJECT STATUS
EXPECTED DELIVERABLES
• Backfilling of basement for casting of the B03 slab
• Casting of columns to the basement 02 100%
• BRC installation for slab casting of B03.
• Columns reinforcement, formworks and casting for the front and back section to be 50% done.
• Procurement arrangements for concrete to cast the raft section made.
• Retaining walls reinforcement, formworks and casting to basement 02 level to be done 100%.